Accomplished Tasks during week 2:
1. Completion of demolition was accomplished.
2. Installation of light fixtures started as scheduled
3. Crew met with architect to confirm location of bench framing wall.
4. AQ provided new bench granite samples to architect.
5. Change order for ceiling supports installation was approved
Upcoming Tasks for week 3:
1. Selection of granite samples from architect.
2. Continue with light fixture installation
3. Start framing for bench and bench wall per architect’s instructions